DisCos Begin Load Recovery After National Grid Collapse …C0NTINUE READING HERE >>>
Power Distribution Companies have begun load recovery following the third collapse of the national grid this week.
Henzodaily gathered that DisCo load, at 2:30 p.m., had increased to 450 megawatts, MW. The target, the National Grid noted, was 4,800 MW.
Below is the latest update on DisCos load:
Abuja DisCo – 80 MW
Benin DisCo – 70 MW
Eko DisCo – 70 MW
Enugu DisCo- 0 MW
Ibadan DisCo – 100 MW
Ikeja DisCo – 130 MW
Jos DisCo- 0 MW
Kaduna DisCo- 0 MW
Kano DisCo- 0 MW
PHarcourt DisCo- 0 MW
Yola DisCo- 0 MW
Total: 450 MW
The grid collapsed for the third time early Saturday morning,…
>